Go to the org/dept page, click on the resource utilization report, then click on the org, select Not Grouped, check show subs, click refresh and all the tasks for all projects show up. Click the column header that says Business Priority (and the business priorities will resort by project name alpha) the header turns blue when done – this may take a few seconds to resort, then click Individual header (this will take a second too-when it is done sorting the header turns blue). Now you have the projects in alpha order so you can scroll to see all the tasks associated with an org and all the names of people who have tasks assigned to them are also in alpha order so you can see by all the tasks owned by team members. Also, you can click on the due date column header– it takes a few seconds -- the tasks are sorted by due date/by task owner/by org.